Olkiluoto 3 is the current new reactor under construction at the [[Olkiluoto NPP]] site.
 +
 +
 
== News from Olkiluoto: ==
 
== News from Olkiluoto: ==
  
Line 17: Line 20:
  
 
TVO, the buyer of the nuclear plant, is very worried that Areva has not been able to catch on schedule. According to the information in december 2007, the estimate for finishing the plant was summer 2011.
 
TVO, the buyer of the nuclear plant, is very worried that Areva has not been able to catch on schedule. According to the information in december 2007, the estimate for finishing the plant was summer 2011.
 +
 +
 +
[[Category: Baltic Map]]
 +
[[Category: Finland]]
 +
[[Category: Nuclear Power Plant]]

Revision as of 17:14, 25 September 2012

Olkiluoto 3 is the current new reactor under construction at the Olkiluoto NPP site.


News from Olkiluoto:

27.1.2009 (Helsingin sanomat)

Siemens leaves Areva NP

Constant problems at Olkiluoto-3 has lead to the fact that Siemens is selling its share of Areva NP to Areva. Unconfirmed data shows that Siemens might try to find a new partner, f.e. Atomenergoprom.


13.1. (YLE)

Olkiluoto-3 is finishes in summer 2012

TVO, the buyer of the nuclear plant, is very worried that Areva has not been able to catch on schedule. According to the information in december 2007, the estimate for finishing the plant was summer 2011.