== 27.1.2009(Helsingin sanomat) ==
+
== 27.1.2009 (Helsingin sanomat) ==
  
  
Line 9: Line 9:
  
 
Constant problems at Olkiluoto-3 has lead to the facts that Siemens is selling its share of Areva NP to Areva. Unconfirmed data shows that Siemens might try to find a new partner, f.e. Atomenergoprom.
 
Constant problems at Olkiluoto-3 has lead to the facts that Siemens is selling its share of Areva NP to Areva. Unconfirmed data shows that Siemens might try to find a new partner, f.e. Atomenergoprom.
 +
 +
 +
== 13.1. (YLE) ==
 +
 +
 +
'''Olkiluoto-3 is finishes in summer 2012'''
 +
 +
TVO, the buyer of the nuclear plant, is very worried that Areva has not been able to catch on schedule. According to the information in december 2007, the estimate for finishing the plant was summer 2011.

Revision as of 07:24, 27 January 2009

News from Olkiluoto:

27.1.2009 (Helsingin sanomat)

Siemens leaves Areva NP

Constant problems at Olkiluoto-3 has lead to the facts that Siemens is selling its share of Areva NP to Areva. Unconfirmed data shows that Siemens might try to find a new partner, f.e. Atomenergoprom.


13.1. (YLE)

Olkiluoto-3 is finishes in summer 2012

TVO, the buyer of the nuclear plant, is very worried that Areva has not been able to catch on schedule. According to the information in december 2007, the estimate for finishing the plant was summer 2011.